PRE CONSTRUCTION STAGE
- Thursday 23rd August 2012 - Initial Building deposit paid
- Tuesday 2nd October 2012 - Tender Appointment paid balance of 3% deposit
- Wednesday 17th October 2012 - Colour, electrical & Tile selection
- Wednesday 24th October 2012 - Contract signing, paid the balance of 5% deposit
- Tuesday 20th November 2012 - Unconditional loan approval
- Wednesday 21st November 2012 - Final Drawings
BASE STAGE - (8 days)
- Tuesday 4th December 2012 - Site Scrape
- Thursday 6th December 2012 - Plumbing
- Monday 10th December 2012 - Boxed ready for slab
- Tuesday 11th December 2012 - Slab poured, received base stage invoice
FRAME STAGE - (9 days
- Wednesday 12th December 2012 - Frame started
- Thursday 20th December 2012 - Frame complete, received frame stage invoice
LOCK UP STAGE (29 days + 3 weeks break for Christmas)
- Friday 21st December 2012 - Finish for the Christmas break
- Friday 11th January 2013 - Bricks delivered
- Monday 14th January 2013 - Return from Christmas break
- Monday 14th January 2013 - Wrapping started
- Tuesday 15th January 2013 - Wrapping complete
- Friday 18th January 2013 - Guttering & plumbing in walls
- Monday 21st January 2013 - Bricking started
- Friday 25th January 2013 - Roof tiles started & almost finished
- Monday 4th February 2013 - Bricks finished, roof tiles finished
- Wednesday 6th February 2013 - solar hot water installed
- Friday 8th February 2013 - Temporary front door and garage internal access door installed, bath frame & cavity sliders
- Monday 11th February 2013 - independent building inspector & shower bases fitted, received lock up stage invoice
FIX STAGE - (31 days)
- Wednesday 13th February 2013 - Electrical
- Friday 15th February 2013 - Ducted heating unit installed, insulation started
- Wednesday 20th February 2013 - Plastering started and finished
- Friday 28th February 2013 - Doors, architraves & skirting delivered
- Monday 4th March 2013 - Rendering done, door frames, doors & architraves started
- Tuesday 5th March 2013 - Doors & Archs finished, skirting started
- Friday 8th March 2013 - Kitchen & all cabinets delivered
- Tuesday 12th March 2013 - Kitchen & all Cabinets installed, skirting finished
- Wednesday 13th March 2013 - Kitchen cabines finished, all internal door hung, front door hung
- Thursday 14th March 2013 - fixing stage invoice received
PRACTICAL COMPLETION STAGE
- Wednesday 27th March 2013 - Internal Painting started
- Tuesday 3rd April 2013 - Internal painting complete
- Wednesday 4th April 2013 - waterproofing
- Thursday 5th April 2013 - Tiling started
- Thursday 11th April 2013 - Tiling completed
- Thursday 18th April 2013 - Casar Stone bench tops put in in the bathroom, ensuite & back bench in the kitchen.
- Monday 22nd April 2013 - Electrical fit off
- Tuesday 23rd April 2013 - Door Handles & door Stops, Casar stone on island bench
- Wednesday 24th April 2013 - Plumbing fit off, toilets installed, heating vents complete
- Thursday 25th April 2013 - Wardrob & pantry fit offs, roof insulation & windows cleaned
- Friday 26th April 2013 - Garage roller door installed
- Monday 29th April 2013 - Shower screens installed
- Tuesday 30th April 2013 - Mirrors installed, fencing taken away, expanders in brickwork complete
- Wednesday 1st May 2013 - Site Clean
- Friday 3rd May 2013 - Timber floor started
- Saturday 4th May 2013 - Timber Floor finished
- Monday 6th May 2013 - Render painted
- Tuesday 7th May 2013 - Underlay laid
- Wednesday 8th May 2013 - Plumber returned to connect bath & finish fit off, External painting
- Thursday 9th May 2013 - Carpet Laid, Tiler returned & finished grout, house cleaned
- Friday 10th May 2013 - Bathrooms sealed, Shower drains out in, external garage door hung, fly screens to all windows
- Monday 13th May 2013 - external painting completed
- Friday 17th May 2013 - Glass splashback, blinds, PCI
- Tuesday 28th May 2013 - Handover