Monday 11th February 2013
Today we were invoiced for "Lock up" Stage
A building inspector had also been to inspect the frame, there was no major issues just some packing required in a few spots & a couple of bowed sections that will need to be fixed
The shower bases have also been fitted in both the bathroom & ensuite
Tuesday 12th February 2013
Today the brackets for all the power points and light switches were mounted & the TV wiring was done
Wednesday 13th February 2013
Today the electrician came and did most of the wiring
Friday 15th February 2013
Today the ducted heating unit was installed
The bath was delivered
And they began the insulation
Plaster is due to start on Tuesday 19th February 2013.