Monday 11 February 2013

Construction - Week 8

Monday 11th February 2013

Today we were invoiced for "Lock up" Stage
A building inspector had also been to inspect the frame, there was no major issues just some packing required in a few spots & a couple of bowed sections that will need to be fixed

The shower bases have also been fitted in both the bathroom & ensuite 



Tuesday 12th February 2013

Today the brackets for all the power points and light switches were mounted & the TV wiring was done




Wednesday 13th February 2013

Today the electrician came and did most of the wiring 







Friday 15th February 2013

Today the ducted heating unit was installed



The bath was delivered


And they began the insulation


Plaster is due to start on Tuesday 19th February 2013.