Sunday 2 December 2012

Time Line


PRE CONSTRUCTION STAGE
  • Thursday 23rd August 2012 - Initial Building deposit paid
  • Tuesday 2nd October 2012 - Tender Appointment paid balance of 3% deposit
  • Wednesday 17th October 2012 - Colour, electrical & Tile selection
  • Wednesday 24th October 2012 - Contract signing, paid the balance of 5% deposit
  • Tuesday 20th November 2012 - Unconditional loan approval
  • Wednesday 21st November 2012 - Final Drawings
 
BASE STAGE - (8 days)
  • Tuesday 4th December  2012 - Site Scrape
  • Thursday 6th December 2012 - Plumbing
  • Monday 10th December 2012 - Boxed ready for slab
  • Tuesday 11th December 2012 - Slab poured, received base stage invoice 


FRAME STAGE - (9 days

  • Wednesday 12th December 2012 - Frame started
  • Thursday 20th December 2012 - Frame complete, received frame stage invoice

 
LOCK UP STAGE (29 days + 3 weeks break for Christmas)
  • Friday 21st December 2012 - Finish for the Christmas break
  • Friday 11th January 2013 - Bricks delivered
  • Monday 14th January 2013 - Return from Christmas break
  • Monday 14th January 2013 - Wrapping started
  • Tuesday 15th January 2013 - Wrapping complete
  • Friday 18th January 2013 - Guttering & plumbing in walls
  • Monday 21st January 2013 - Bricking started 
  • Friday 25th January 2013 - Roof tiles started & almost finished
  • Monday 4th February 2013 - Bricks finished, roof tiles finished
  • Wednesday 6th February 2013 - solar hot water installed
  • Friday 8th February 2013 - Temporary front door and garage internal access door installed, bath frame & cavity sliders 
  • Monday 11th February 2013 -  independent building inspector & shower bases fitted, received lock up stage invoice

FIX STAGE - (31 days)

  • Wednesday 13th February 2013 -  Electrical 
  • Friday 15th February 2013 - Ducted heating unit installed, insulation started 
  • Wednesday 20th February 2013 - Plastering started and finished
  • Friday 28th February 2013 - Doors, architraves & skirting delivered

  • Monday 4th March 2013 - Rendering done, door frames, doors & architraves started
  • Tuesday 5th March 2013 - Doors & Archs finished, skirting started
  • Friday 8th March 2013 - Kitchen & all cabinets delivered
  • Tuesday 12th March 2013 - Kitchen & all Cabinets installed, skirting finished
  • Wednesday 13th March 2013 - Kitchen cabinets finished, all internal door hung, front door hung
  • Thursday 14th March 2013 - fixing stage invoice received

PRACTICAL COMPLETION STAGE

  • Wednesday 27th March 2013 - Internal Painting started

  • Tuesday 3rd April 2013 - Internal painting complete
  • Wednesday 4th April 2013 - waterproofing
  • Thursday 5th April 2013 - Tiling started
  • Thursday 11th April 2013 - Tiling completed
  • Thursday 18th April 2013 - Caesar stone bench tops in the ensuite, bathroom & back kitchen bench put in
  • Monday 22nd April 2013 - Electrical fit off
  • Tuesday 23rd April 2013 - Door Handles & door Stops, Caesar stone on island bench
  • Wednesday 24th April 2013 - Plumbing fit off, toilets installed, heating vents complete
  • Thursday 25th April 2013 - Wardrobe & pantry fit offs, roof insulation & windows cleaned 
  • Friday 26th April 2013 - Garage roller door installed 
  • Monday 29th April 2013 - Shower screens installed
  • Tuesday 30th April 2013 - Mirrors installed, fencing taken away, expanders in brickwork complete

  • Wednesday 1st May 2013 - Site clean
  • Friday 3rd May 2013 - Timber floor started
  • Saturday 4th May 2013 - Timber Floor finished
  • Monday 6th May 2013 - Render painted
  • Tuesday 7th May 2013 - Underlay laid
  • Wednesday 8th May 2013 - Plumber returned to connect bath & finish fit off, External painting
  • Thursday 9th May 2013 - Carpet Laid, Tiler returned & finished grout, house cleaned
  • Friday 10th May 2013 - Bathrooms sealed, Shower drains out in, external garage door hung, fly screens to all windows
  • Monday 13th May 2013 - External painting completed
  • Friday 17th May 2013 - Glass splashback, blinds, PCI
  • Tuesday 28th May 3013 - Hand over



1 comment:

  1. Our timeline mirrors yours but we are way behind... you must have a good building coordinator. Good Luck.