Monday 21st January 2013
Finally 11 days after being delivered, bricking has began 3/4 of the garage side garage wall has been done as well as the front left of the garage
Tuesday 22nd January 2013
Bricking continues, today the front portico was bricked as well as the pillar on the alfresco
Wednesday 23rd January 2013
Bricking on the left side of the house was started today.
The Windows & roof titles were also delivered
Thursday 24th January 2013
Today bricking was started on the back of the house as well as the right side
Friday 25th January 2013
Roof tiles were pretty much started & finished today as well as some more bricking
Tuesday 22nd January 2013
Bricking continues, today the front portico was bricked as well as the pillar on the alfresco
Wednesday 23rd January 2013
Bricking on the left side of the house was started today.
The Windows & roof titles were also delivered
Thursday 24th January 2013
Today bricking was started on the back of the house as well as the right side
The windows & doors were also installed and the roof trusses covered and ready for tiles
Friday 25th January 2013
Roof tiles were pretty much started & finished today as well as some more bricking