Monday 8 April 2013

Construction - Week 16

Monday 8th April 2013
 
Today the rest of the floor tiles were laid as well as the top of the bath. The titles skirting is still to be done as is the showers & splashbacks in both the bathrooms & laundry


Tuesday 9th April 2013

Today the titled skirting & the grout in the Laundry was completed, leaving only the splash back to be done in this room

 
In the toilet & bathroom the tiled skirting was also completed, the tiles on the side of the bath have been done minus 1 tile (i'm not sure why) & the shower has been tiled as well but hasn't got grout.
 
No tiling has been done in the ensuite today.
 
 
Wednesday 10th April 2013
 
Today was more tiling, the ensuite skiting has been complete and the floor grouted. The shower has also been tiled but is still waiting for grout.
 
 
 
The toilet appears to be complete as well as the bathroom apart from the tiled splashback as we are waiting for the bench tops to arrive which have been delayed and wont be here until the end of next week
 
The laundry has also been finished and we are very happy with the way it has all come together.
 
 
 

2 comments:

  1. Hi Belinda
    Everything is looking great above and a pity about the hassles you are having now (start of May).
    May I ask, the shower drains - did you request them to be the long drain or is this just how they do them now? I noted a comment from someone on homeone forum and I am just not sure?

    ReplyDelete
  2. Hi Mumma Deb,
    No we didn't request them to be long drains it is just how they did them.

    ReplyDelete