Wednesday 18 September 2013

3 Month Inspection

Its hard to believe we have already been in our house for 3 months (actually almost 4)
We had our 3 month inspection on Tuesday 17th September 2013 and the following issues were reported:
 
 
Master Ensuite
 
Calcium build up along ensuite shower wall to be removed and
rectified. Ensuite shower is also leaking to left hand side of plaster to
be tested with mc on site

 

 





Ensuite shower is leaking. Inspect with paddy the tiler and repair
damages to left hand side plaster of ensuite wall


 


 
Master Bedroom
 
Adjust master bedroom door. Latches catching on striker plate
















Entry, Front Hallway & Bedroom 3
Paint touch ups to left hand side of hallway as marked at PCI to be
completed. Touch ups missed and noted by supervisor
Paint touch ups required to the hallway 45 degree angle wall.
Paint touch ups as written on PCI missed by supervisor
 
Bedroom three paint touch us to be rectified to right hand wall. Left
over from construction
 
 


 

Toilet
 
Plumbers to inspect wire sticking out to base of toilet and to silicone
around toilet base









 

 
Bathroom
Rusty water escaping through bathroom. Bath tub fitting is spraying
out rust water. Issue to be inspected and rectified
















 
Alfresco

Supervisor to paint alfresco concrete as discussed with client.
Supervisor to complete these works
 
















Exterior

Paint touch up to scratched downpipe at rear of garage






 